Summary: In PMP® Exam questions, the Earned Value Management (EVM)
questions are usually considered the most important ones as candidates will
need to solve quite a few of them in the real PMP® Exam — I got around 7
EVM questions on my PMP® Exam paper and I am quite confident that I could get
them all correct.
EVM is not a PMI Method; it was
introduced by the military to manage large scale military projects. It is applicable to many other industries and
projects.
When should it be used? Never for Firm Fixed price contracts, costs
are known by the buyer and they are fixed, it will only give schedule
information. EVM is expensive, so there is no need to add the additional cost.
Cost Plus and Time and Materials type contracts that meet cost thresholds are
where EVM become useful.
However, many project managers may
not have done any EVM in their projects and many of them consider the EVM
questions a bit scary.
This post aims to help PMP®
aspirants to understand easily the EVM concepts and how to tackle the EVM
questions.
Introduction
As project managers come from
different backgrounds, there is no consensus for the level of difficulty of EVM
questions. But if you can understand the concepts of EVM firmly, you too will find that EVM
questions for the PMP® Exam is indeed NOT difficult at all. After all, the
PMP® Exam is not an exam decided for Maths students, the PMP® Exam tests your
understanding of project management as a whole.
To arrive at the correct answers for EVM questions, all you need
to do in the PMP® Exam is to:
1.
Read the question carefully and understand correctly
2.
Choose the correct formula to apply
3.
Calculate the answer
EVM Concepts
Explained With Examples
Earned value management (EVM) is used to assess the schedule
and cost performance of a project — with EVM, the project manager will
know exactly whether the project is with respect to schedule and budget
Schedule -
§ ahead of schedule
§
on Schedule
§
behind the schedule
Budget
§
under budget
§
on Budget
§
over budget
Earned value management (EVM) bases on the concept that i) work
completed will deliver value and ii) the value delivered equals the budget put
into the work. The value gained can be assessed along the progression of the
project. In reality, earned value management is very complicated as value
usually cannot simply be assessed based on the percentage of completion.
PMI has simplified PMP® EVM calculation to
very “ideal” situations! You will just need to know the following to get your
PMP® EVM questions correct.
Basic EVM
Formulas
To speak more clearly how the value
is to be managed, a number of terms are defined in EVM (explained with the example of building 10 houses each has a
value of US$500 expected to be completed in 10 weeks in proportion):
§
Planned Value (PV) — The budgeted value of the
work completed so far at a specific date
example: at end of week 4, altogether 4 houses should be completed, the PV is US$2000
example: at end of week 4, altogether 4 houses should be completed, the PV is US$2000
§
Earned Value (EV) — The actual value of the
work completed so far at a specific date (refer to the “Notes on
Earned Value Measurement” section below)
example: by end of week 4, only 3 houses are completed, the EV is US$1500
example: by end of week 4, only 3 houses are completed, the EV is US$1500
§
Actual Cost (AC) — The total expenditure for the
work so far at a specific date
example: by end of week 4, US$2000 was spend, the AC is US$2000
example: by end of week 4, US$2000 was spend, the AC is US$2000
EVM is based on monitoring these three aspects along the
project in order to reveal the health of the project with the following
indices:
§
Schedule Variance (SV) — difference between PV and EV,
to tell whether the project work is ahead of / on / behind schedule
§
SV = EV – PV
If the project is behind schedule the SV will be negative (i.e. achieved less than what planned)
If the project is on schedule the SV = 0
If the project is ahead of schedule the SV will be positive (i.e. achieved more than what planned)
If the project is behind schedule the SV will be negative (i.e. achieved less than what planned)
If the project is on schedule the SV = 0
If the project is ahead of schedule the SV will be positive (i.e. achieved more than what planned)
example: by end of week 4, the SV = EV – PV = US$1500 – US$2000 =
-US$500 (behind schedule)
§
Schedule Performance Index (SPI) — ratio between EV and PV, to
reflect whether the project work is ahead of / on / behind schedule in relative terms
§
SPI = EV/PV
If the project is behind schedule the SPI < 1 (i.e. achieved less than what planned)
If the project is on schedule the SPI = 1
If the project is ahead of schedule the SPI > 1 (i.e. achieved more than what planned)
If the project is behind schedule the SPI < 1 (i.e. achieved less than what planned)
If the project is on schedule the SPI = 1
If the project is ahead of schedule the SPI > 1 (i.e. achieved more than what planned)
§ example: by end of week 4, the SPI = EV/PV = US$1500/US$2000 = 0.75
(behind schedule)
§
Cost Variance (CV) — difference between
PV and AC, to tell whether the project work is under / on / over budget
§
CV = EV – AC
If the project is over budget the CV will be negative (i.e. achieved less than spent)
If the project is on budget the CV = 0
If the project is under budget the CV will be positive (i.e. achieved more than spent)
If the project is over budget the CV will be negative (i.e. achieved less than spent)
If the project is on budget the CV = 0
If the project is under budget the CV will be positive (i.e. achieved more than spent)
§ example: by end of week 4, the CV = EV – AC = US$1500 – US$2000 = -US$500
(over budget)
§
Cost Performance Index (CPI) — ratio
between EV and AC, to reflect whether the project work is under / on / over budget in relative terms
§
CPI = EV/AC
If the project is over budget the CPI < 1 (i.e. achieved less than spent)
If the project is on budget the CPI = 1
If the project is under budget the CPI > 1 (i.e. achieved more than spent)
If the project is over budget the CPI < 1 (i.e. achieved less than spent)
If the project is on budget the CPI = 1
If the project is under budget the CPI > 1 (i.e. achieved more than spent)
§ example: by end of week 4, the CPI = EV/AC = US$1500/US$2000 = 0.75 (over
budget)
Note both SV and SPI / CV and CPI give similar
information on schedule / budget but the indices will give more insights into
the actual performance with a meaning comparison.
From my experience, the most difficult process of solving
EVM problems for PMP® Exams is to identify the PV, EV and AC from the wordy
calculation questions. Then you will just have to recall the correct formula to
substitute the values into to get the answer — the question will usually ask
you directly about the actual indices to get.
Advanced EVM
Formulas
§
Budget at Completion (BAC) — also known as the
project/work budget, that is the total amount of money originally planned to
spend on the project/work
§ example: the BAC for the housing
project = US$500 x 10 = US$5000
§
Estimate at completion (EAC) — as the project goes on, there
may be variations into the actual final cost from the planned final cost, EAC
is a way to project/estimate the planned cost at project finish based on the currently
available data
§
The following formulas can be used to calculate EAC based on
which information and conditions given in the question:
§
EAC = BAC/CPI
If we believe the project will continue to spend at the same rate up to now
If we believe the project will continue to spend at the same rate up to now
§
The delay is caused by reasons which is likely to continue (e.g.
labor with less skilled than expected)
§ example: the EAC for the housing
project = US$5000 / 0.75 = US$6666.66
§
EAC = AC + (BAC-EV)
If we believe that future expenditures will occur at the original forecasted amount (no more delays of the same kind in future)
If we believe that future expenditures will occur at the original forecasted amount (no more delays of the same kind in future)
§
The delay might be caused by some unforeseen reasons (e.g.
typhoon) which is not likely to happen again
§ example: the EAC for the housing
project = US$2000 + (US$5000 – $1500) = US$5500
§
EAC = AC + [(BAC-EV)/(SPI*CPI)]
If we believe that both current cost and current schedule performance will impact future cost performance
If we believe that both current cost and current schedule performance will impact future cost performance
§
The performance of the project will continue with sub-prime
standards (over budget and behind schedule)
§
This formula is less likely to be used for the PMP® Exam
§
example: the EAC for the housing project = US$2000 + [(US$5000 – $1500)/(0.75*0.75)]
= US$8222
§
EAC = AC + New Estimate
If we believe the original conditions and assumptions are wrong
If we believe the original conditions and assumptions are wrong
§
Will not be tested as there is nothing to calculate
§
Variance at Completion (VAC) — the variance at
completion, i.e. the difference between the new estimate at completion and
original planned value
§
VAC = BAC – EAC
If we forecast the project will be over budget, VAC will be negative
If we forecast the project will be under budget, VAC will be positive
If we forecast the project will be over budget, VAC will be negative
If we forecast the project will be under budget, VAC will be positive
§ example: the VAC for the housing
project = US$5000 – US$6666 (just take the 1st EAC as an example only) = -US$1666
§
To Complete Performance Index (TCPI) — the
efficiency needed to finish the project on budget, it is the ratio
between budgeted cost of work remaining and money remaining
§
TCPI = (BAC-EV)/(BAC-AC)
Use this equation if the project is required to finish within BAC
Use this equation if the project is required to finish within BAC
§ example: the TCPI for the
housing project at end of week 4 = (US$5000 – US$1500) / (US$5000 – US$2000) =
1.16
§
TCPI = (BAC-EV)/(EAC-AC)
Use this equation if the project is required to finish within new EAC
Use this equation if the project is required to finish within new EAC
§ example: the TCPI for the housing
project at end of week 4 with new EAC US$6666 = (US$5000 – US$1500) / (US$6666
– US$2000) = 0.75
Notes on Earned
Value Measurement
The following will discuss how earned value is measured for
project and work, from simple physical measurements, percentage complete to
weighted milestones. Since the PMP® EVM questions cannot describe a lot of
information, the part on earned value measurements will normally be based on
simplified situations like physical measurements or percentage complete.
It is likely that you will not be tested on the more difficult
ways of measuring earned values. These are included here for your reference
only.
§
Physical Measurement — directly
transform the physical measurement of the amount of work completed
into EV
§ example: building 10 houses each
has a value of US$500 expected to be completed in 10 weeks in proportion,
earned value of 3 house built is US$1500
§
Percentage Complete — directly transform the percentage
of the amount of work completed into EV
§ example: building 10 houses each
has a value of US$500 expected to be completed in 10 weeks in proportion,
earned value of 30% complete is US$1500
§
Weighted Milestone — a EV is assigned to the 100%
completion of each milestone of the work packages with prior agreement with
stakeholders
§
Fixed Formula — a specific percentage of the
overall PV is assigned to the start of a work package and the remaining
assigned upon completion; these must be agreed upon in the project
management plan
§
0/100 rule: 0% EV at the activity begins; 100% EV
upon completion
§
20/80 rule: 20% EV at the activity begins; 80% EV upon
completion.
§
50/50 rule: 50% EV at the activity begins; 50% EV upon
completion
EVM Charts
In common practices, EVM will also involve plotting the values
on a graph in order to help stakeholders concerned to visualize the progress
and the health of the project. More often than not you will find the
EV, AC and PV plotted on a graph and you will be asked on the interpretation of
the graph.
Insights to be gained from the chart:
§
If EV line is below PV, the project is behind schedule; if EV is
above PV, the project is ahead of schedule.
§
If AC line is below EV, the project is within budget; if AC is
above EV, the project is over budget.
Below is an example of the EVM charts you would be likely to
encounter in your PMP® Exam — solid lines represent actual figures while dotted
lines represent forecasted figures:
Judging from the chart above,
we can infer that the project is currently over budget and behind
schedule.
PMP®
Earned Value Management (EVM) Formulas in PMBOK® Guide At a Glance
Name
(Abbreviation)
|
Formula
|
Interpretation
|
Schedule Performance Index
(SPI)
|
SPI = EV/PV
EV = Earned Value
PV = Planned Value |
< 1
behind schedule
= 1 on schedule > 1 ahead of schedule |
Cost Performance Index (CPI)
|
CPI = EV/AC
EV = Earned Value
AC = Actual Cost |
<
1 Over budget
= 1 On budget > 1 Under budget sometimes the term ‘cumulative CPI’ would be shown, which actually is the CPI up to that moment |
Schedule Variance (SV)
|
SV = EV – PV
EV = Earned Value
PV = Planned Value |
< 0
Behind schedule
= 0 On schedule > 0 Ahead of schedule |
Cost Variance (CV)
|
CV = EV – AC
EV = Earned Value
AC = Actual Cost |
< 0
Over budget
= 0 On budget > 0 Within budget |
Estimate at Completion (EAC) if original is flawed
|
EAC = AC + New ETC
AC = Actual
Cost
New ETC = New Estimate to Completion |
if the original
estimate is based on wrong data/assumptions or circumstances have changed
|
Estimate at Completion (EAC) if BAC remains the same
|
EAC = AC + BAC – EV
AC = Actual Cost
BAC = Budget at completion EV = Earned Value |
the variance is
caused by a one-time event and is not likely to happen again
|
Estimate at Completion (EAC) if CPI remains the same
|
EAC = BAC/CPI
BAC = Budget at completion
CPI = Cost performance index |
if the CPI would
remain the same till end of project, i.e. the original estimation is not
accurate
|
Estimate at Completion (EAC) if substandard performance continues
|
EAC = AC + [(BAC
-EV)/(CPI*SPI)]
AC = Actual
Cost
BAC = Budget at completion EV = Earned Value CPI = Cost Performance Index SPI = Schedule Performance Index |
use when the question gives
all the values (AC, BAC, EV, CPI and SPI), otherwise, this formula is not
likely to be used
|
To-Complete Performance Index
(TCPI)
|
TCPI = (BAC – EV)/
(BAC – AC)
BAC = Budget at completion
EV = Earned value AC = Actual Cost
TCPI = Remaining Work
/Remaining Funds
BAC = Budget at
completion
EV = Earned value CPI = Cost performance index |
<
1 Under budget
= 1 On budget > 1 Over budget |
Estimate to Completion
|
ETC = EAC -AC
EAC = Estimate at Completion
AC = Actual Cost |
|
Variance at Completion
|
VAC = BAC – EAC
BAC = Budget at completion
EAC = Estimate at Completion |
< 0
Over budget
= 0 On budget > 0 Under budget |
12 PMP® EVM
Formulas
|
Hint - Make sure you understand about
CV, SV, CPI and SPI,
EV Comes first in each of these formulas. Remembering this
would help you to clear at least half of the earned value questions right.
References – PMBOK® , RMC, Internet Content
References – PMBOK® , RMC, Internet Content
No comments:
Post a Comment